Bottom-of-dam plant on the Pisuerga river, at the Requejada reservoir, in Cervera de Pisuerga, Palencia. It was built in 1950 and it holds an installed power of 5 MW in a Kaplan turbine.
The connection point is located in Guardo, and the energy is evacuated via a 19 km line to Camporredondo and from there to our substation.
Head is 59 m and flow 10.2 m3/s.